Temporary placement of wooden mats as working surface in
wet areas near Three Mile Branch |
11/23/2009 |
|
Rip-rap placed at discharge at Three Mile Branch |
12/9/2009 |
|
Area where hydraulic barrier swale will be constructed |
12/15/2009 |
|
Large rip-rap for construction of Grade Control
Structures |
12/23/2009 |
|
Preparation for excavation of Constructed Wetlands |
1/5/2010 |
 |
Preliminary excavation for Constructed Wetlands |
1/6/2010 |
 |
Preliminary excavation for Constructed Wetlands |
1/6/2010 |
 |
Preliminary excavation for Constructed Wetlands |
1/6/2010 |
 |
Excavation for Constructed Wetland |
1/7/2010 |
 |
Excavation for Constructed Wetland |
1/12/2010 |
 |
Building Constructed Wetland |
2/10/2010 |
 |
Building Constructed Wetland |
2/10/2010 |
 |
Building Constructed Wetland |
2/10/2010 |
 |
Building Constructed Wetland |
2/10/2010 |
 |
Building Constructed Wetland |
2/10/2010 |
 |
Area north of Northern Boulevard before construction of
rip-rap basin |
3/8/2010 |
 |
Temporary construction bridge |
3/8/2010 |
 |
Planting in constructed wetland |
3/8/2010 |
 |
Planting in constructed wetland |
3/8/2010 |
 |
Planting in constructed wetland |
3/8/2010 |
 |
Root wads in Lower Kilby Ditch |
3/8/2010 |
 |
Head of hydraulic barrier swale before slope
stabilization |
3/8/2010 |
 |
Construction of hydraulic barrier swale |
3/8/2010 |
 |
Construction of hydraulic barrier swale |
3/8/2010 |
 |
Outfall at Three Mile Branch |
3/8/2010 |
 |
Outfall at Three Mile Branch |
3/8/2010 |
 |
Inlet into constructed wetland |
3/15/2010 |
 |
Outlet from constructed wetland |
3/15/2010 |
 |
Hydraulic barrier swale |
3/15/2010 |
 |
View of hydraulic barrier swale from north |
3/18/2010 |
 |
View of hydraulic barrier swale from north |
3/18/2010 |
 |
View of hydraulic barrier swale from north |
3/18/2010 |
 |
Box culverts under North Boulevard after cleaning |
3/18/2010 |
 |
Constructed wetland |
3/18/2010 |
 |
Plants in constructed wetland |
3/18/2010 |
 |
Head of hydraulic barrier swale after slope
stabilization |
3/23/2010 |
 |
Hydraulic barrier swale |
3/23/2010 |
 |
Inlet into constructed wetland |
3/25/2010 |
 |
North gravel road |
3/25/2010 |
 |
Hydraulic barrier swale |
3/30/2010 |
 |
Hydraulic barrier swale |
3/30/2010 |
 |
Discharge at Three Mile Branch |
3/30/2010 |
 |
Constructed wetland |
3/30/2010 |
 |
Construction of rip-rap basin north of Northern
Boulevard |
3/30/2010 |
 |
Construction of rip-rap basin north of Northern
Boulevard |
3/30/2010 |
 |
Live stakes for holding rolled erosion control matting
and vegetation establishment |
4/7/2010 |
 |
Live stakes for holding rolled erosion control matting
and vegetation establishment |
4/7/2010 |
 |
Live stakes for holding rolled erosion control matting
and vegetation establishment |
4/7/2010 |
 |
Live stakes for holding rolled erosion control matting
and vegetation establishment |
4/7/2010 |
 |
Tie in of hydraulic barrier swale to Kilby Ditch |
4/7/2010 |
 |
Temporary construction bridge across hydraulic barrier
swale |
4/7/2010 |
 |
Constructed wetland |
4/7/2010 |
 |
Completed rip-rap basin north of Northern Boulevard |
4/7/2010 |
 |
Construction of J-Hook (grade control structure) |
4/13/2010 |
 |
Placement of stone for J-Hook |
4/13/2010 |
 |
Saw cutting of stone for grade control structures |
4/13/2010 |
 |
Checking elevations of J-Hook |
4/13/2010 |