Construction of fence in Upper Kilby area prior to construction Construction of fence in Upper Kilby area prior to construction 9/23/2009
Construction of fence in Upper Kilby area prior to construction Construction of fence in Upper Kilby area prior to construction 9/23/2009
Clearing in Upper Kilby area prior to construction Clearing in Upper Kilby area prior to construction 9/23/2009
Protection of monitoring wells with barracades Protection of monitoring wells with barricades 9/23/2009
Construction entrance Construction entrance 9/23/2009
Construction of pad for containment area Construction of pad for containment area 9/24/2009
Welding of liner seams for containment area Welding of liner seams for containment area 9/29/2009
Construction of liner system for containment area for soil dewatering and water treatment Construction of liner system for containment area for soil dewatering and water treatment 9/30/2009
Construction of liner system for containment area for soil dewatering and water treatment Construction of liner system for containment area for soil dewatering and water treatment 9/30/2009
Construction of liner system for containment area for soil dewatering and water treatment Construction of liner system for containment area for soil dewatering and water treatment 9/30/2009
Construction of liner system for containment area for soil dewatering and water treatment Construction of liner system for containment area for soil dewatering and water treatment 9/30/2009
Staging of construction materials for project Staging of construction materials for project 9/30/2009
Placement of water treatment containers Placement of water treatment containers 10/5/2009
Construction of equipment decontamination area Construction of equipment decontamination area 10/6/2009
Delivery of soil dewatering boxes Delivery of soil dewatering boxes 10/8/2009
Connecting soil dewatering containers to treatment system Connecting soil dewatering containers to treatment system 10/8/2009
Containment area with soil dewatering boxes Containment area with soil dewatering boxes 10/13/2009
Containment area with soil dewatering boxes and water treatment tanks Containment area with soil dewatering boxes and water treatment tanks 10/13/2009
Containment area with soil dewatering boxes Containment area with soil dewatering boxes 10/13/2009
Liner installation for containment area Liner installation for containment area 10/13/2009
Unloading of soil into soil dewatering boxes Unloading of soil into soil dewatering boxes 10/22/2009
Staging of construction materials for project Staging of construction materials for project 11/3/2009
Containment system with soil dewatering boxes and water treatment system Containment system with soil dewatering boxes and water treatment system 11/3/2009
Safety briefing for Community Outreach Group prior to construction tour Safety briefing for Community Outreach Group prior to construction tour 11/3/2009
Safety briefing for Community Outreach Group prior to construction tour Safety briefing for Community Outreach Group prior to construction tour 11/3/2009
Safety briefing for Community Outreach Group prior to construction tour Safety briefing for Community Outreach Group prior to construction tour 11/3/2009
Soil dewatering boxes during construction Soil dewatering boxes during construction 11/5/2009
Decontamination of equipment prior to demobilization from site Decontamination of equipment prior to demobilization from site 12/29/2009